Brazil Wants to Restart Work on Nuclear Plant Paralyzed in 1988

The director of Planning, Management and Environment at Eletronuclear – the Brazilian company that operates the Angra 1 and 2 nuclear power plants – LuÀ­s Hiroshi Sakamoto, says that Brazil will need another nuclear power plant to meet the demand.

That nuclear power plant is Angra 3, which, along with Angra 1 and 2, went into construction during the military administrations (1964-85).

Angra 1 and 2 have been completed and are operational, but Angra 3, scheduled to be operating in 1988, was never finished although US$ 750 million was spent on it.

It is estimated it costs US$ 20 million just to maintain it in its present state, and will take another US$ 1.8 billion and five years to complete.

All three of Brazil’s nuclear power plants are located closely together at a beach resort, Angra dos Reis, on the coast of the state of Rio de Janeiro 150 kilometers from the city of Rio de Janeiro.

Sakamoto points out that because they are clean, the use of nuclear power plants around the world means that two billion tons of carbon dioxide have not been pumped into the atmosphere, aggravating the greenhouse effect.

As for Angra 3, Sakamoto says Brazil has the know-how to conclude the construction and is ready to do so. "The country is going to need more energy and Angra 3 is an obvious candidate to supply it," he said.

The Brazilian official added that the fact that construction on it has already begun is a positive point. "What has been paid for is paid for. We will move ahead from where we are. There is no need to start from scratch. It means building Angra 3 will cost less than a similar plant anywhere in the world."

Sakamoto says that at the moment nuclear power (Angra 1 and 2) supplies 40% of the electricity used in the state of Rio de Janeiro. With Angra 3 in operation, that percentage will rise to 70%.

Agência Brasil

Tags:

You May Also Like

IMF Cites Brazil as Model for Latin America

On the verge of a decision about a possible new agreement with Brazil, the ...

Experts Call US$ 20 Bi Brazil-Venezuela Gas Pipeline a Pipe Dream

Petroleum and energy experts seriously questioned this week Venezuela, Brazil and Argentina’s project to ...

Brazil Wants to Create a South American Interpol

The Brazilian government is sponsoring the creation of a Mercosur police force similar to ...

Daily Doses of Foreign Cash Keep Brazil’s Comatose Varig Alive

VarigLog made another deposit yesterday, July 3, to keep bankrupt Brazilian airline Varig operating ...

Sugarcane Fields in Brazil Have Become Killing Fields

As countries look to reduce toxic emissions from cars, many are promoting a fuel ...

Foreign Market for Brazilian Chicken Grows 40%

The Brazilian Poultry Exporters Association (Abef) estimates that chicken exports up to the end ...

Brazil Plans on Reducing the Greenhouse Effect Through Fertilizers

Brazilian researchers at the Ministry of Science and Technology, the Brazilian Farm Research Corporation ...

Brazil-Arab Trade Exceeding Expectations

Brazilian exports to the Arab countries grew 18% in the first months of this ...

Brazil: How Bolsa-Escola Made a Difference in Selma’s Life

On an unwalled lot enclosed by barbed wire, Selma Ferreira Rodrigues’s shack sheltered her ...

Highways in Brazil: a Dead-end Road

Anyone entering a car, truck, or bus and driving on the Brazilian highways knows ...